Micro-Generation Connection Process (Net Metered Generation < 10kW)

The process below is required for all new micro-generation, net metered applications < 10kW. For projects over 10kW, please follow the process here.

Once  you’ve received the Preliminary Consultation Report from Elexicon indicating the project can proceed, the customer will need to complete the following documents provided by Elexicon in order to move forward with the project:

  • Application to Connect Embedded Generation Facility
  • Micro Generation Agreement
  • Single Line Diagram

The customer completes and sends the package back by email to dservices@elexiconenergy.com

  • Elexicon will proceed with completing a service layout and offer to connect for the project. This documentation outlines the required construction and costs. Elexicon will email the completed service layout and offer to connect to the customer within sixty (60) days of receiving all required items.
  • The customer reviews and signs the offer to connect, paying any required fees. The customer may begin to work on their project. The customer must coordinate Connection Authorization with the Electrical Safety Authority (ESA).
  • Elexicon will proceed with the net meter installation once the following are received:
    • Signed Offer to Connect
    • Payment
    • ESA Authorization